Quick answer

An 80 lb bag yields about 0.6 cu ft. A 10×10 ft slab at 4 inches needs 56 bags, which is 1.23 cubic yards.

10 ft × 10 ft4 in10 ft56 bagsof 80 lb mix1.23 cu yd
Slab thickness and bag count

Slabs and post holes use different geometry but the same bag math. Enter the shape and get bags for both 60 lb and 80 lb mixes.

Bagged concrete is sold by weight and yields by volume: an 80 lb bag makes about 0.6 cubic feet, a 60 lb bag about 0.45. The whole calculation is therefore volume first, bags second, with no allowance for spillage because bags are already rounded up.

Above roughly one cubic yard — about 45 bags of 80 lb — a ready-mix truck is usually cheaper and much faster. For a 10 × 10 ft slab at 4 inches you are right at that boundary, which is why the calculator flags it.

Formula and assumptions

How the calculation works

  • Slab volume (cu ft) = length × width × (thickness in inches ÷ 12)
  • Post hole volume = π × radius² × depth × number of holes (all in feet)
  • 80 lb bags = cubic feet ÷ 0.6; 60 lb bags = cubic feet ÷ 0.45
  • Cubic yards = cubic feet ÷ 27

Worked example

Worked example: a 10 × 10 ft slab at 4 inches
Volume: 10 × 10 × (4 ÷ 12) = 33.3 cu ft
Cubic yards: 33.3 ÷ 27 = 1.23 cu yd
80 lb bags: 33.3 ÷ 0.6 = 55.6, round up to 56
60 lb bags: 33.3 ÷ 0.45 = 74.1, round up to 75

56 bags of 80 lb mix, or 75 bags of 60 lb. Compare ready-mix delivery at this size.

Quick reference

80 lb bags for a 4 inch slab
SlabCubic feetCubic yards80 lb bags
4 × 4 ft5.30.209
6 × 6 ft12.00.4420
8 × 8 ft21.30.7936
10 × 10 ft33.31.2356
12 × 12 ft48.01.7880

Common questions

How many 80 lb bags are in a cubic yard?

About 45. A cubic yard is 27 cubic feet and each 80 lb bag yields 0.6 cubic feet.

How much water per bag?

Use the amount printed on the bag, usually 2.5–3 quarts for an 80 lb bag. Extra water weakens the mix and causes cracking.

Do I need rebar or mesh?

Slabs on grade usually get welded wire mesh or rebar on chairs. Post holes generally need none, but check local code for structural work.

How long before I can walk on it?

Light foot traffic after 24 hours, vehicles after about 7 days. Full cure takes 28 days.

Can I pour in cold weather?

Below 40°F the mix sets slowly and can freeze. Use cold-weather mix and keep the pour covered; avoid pouring into frozen ground.